Case Studies / Banking
Banking · Oracle RACBank failover in under 10 minutes — down from hours.
Two-node Oracle RAC for a district cooperative bank — high availability engineered onto commodity hardware.
98.5%
Uptime (first 6 months)
<10 min
Failover
Zero
Critical outages
The ClientBellary District Co-operative Central Bank (BDCC), Karnataka — via SoftBee Consultancy Services.
01
The Challenge
A single-node database ran the bank.
✕Frequent downtime and application instability
✕No real-time failover; recovery measured in hours
✕Flat network without public/private separation
02
What We Built
A properly engineered two-node Oracle RAC cluster.
✓Dell PowerEdge servers + PowerVault SAN over Fibre Channel
✓Oracle ASM volumes (database / archive logs / OCR registry)
✓Dual public/private cluster networking with VIPs and SCAN
✓RHEL 6.10, Oracle 11g
03
The Stack
Oracle 11g RACASMRHELDell PowerEdge/PowerVaultFibre Channel
04
The Results
Numbers from production operation — not projections.
98.5%
Uptime in the first six months
<10 min
Failover recovery (from hours)
Zero
Critical outages since go-live
Their team engineered bulletproof High Availability architectures for our DC/DR setup, combining technical brilliance with relentless dedication.K Raghavendra KamathDirector, SoftBee Consultancy Services Pvt. Ltd.
MORE
Related case studies
Banking · High Availability
Planned maintenance, zero downtime — cooperative banking on Oracle RAC.
98% Uptime · Zero-downtime MaintenanceAutomotive · Fortune 500One bad test change can stop a production line. This supplier made that impossible.
Up to 50% Less downtime · 100+ Machines governedTelecom · SD-WAN & SASEEvery SD-WAN vendor built a walled garden. We gave one MSP a single gate.
40% Less training time · 20% Faster deploymentsYour platform next
Building something this hard?
Tell us what you're building. A senior engineer — not a sales rep — replies within one business day.